Rakaia wastewater project ready for commissioning stage

Twelve new sludge-drying beds at the Rakaia wastewater treatment plant will soon be in use.
The beds will ensure Council complies with Environment Canterbury consents to operate the wastewater plant.
Infrastructure and Open Spaces Group Manager Neil McCann said the $1.23 million project was on time and commissioning of the beds would begin next week.
“We’re really pleased with the job done by Grant Hood Contracting, as there were some unique design and specification features of this project.”
The beds use a combination of evaporation and gravity drainage through sand-lined concrete bunkers to dewater sludge from Rakaia’s wastewater. Once dried, the sludge will be removed to landfill.
Mr McCann said the 12 concrete drying beds were each about 100m2 in area.
“The 12 beds will work in rotation and we expect two beds will need to be cleaned every two weeks, given the volume of wastewater Rakaia produces. Removing it regularly means there is less risk of odour and Council will be meeting the strict rules about managing municipal wastewater.”
Once sludge is deposited into the drying bed, the liquid drains through a filter of three layers of sand and gravel; the sludge remains on top to dry and is scraped off by a digger when it reaches about 20cm deep, and sent to landfill.
The filtered liquid is pumped back to the wastewater plant’s clarifier where it will be treated before being sprayed onto adjacent land.
Operation and maintenance costs of the beds will be about $90,000 a year.
The drying beds should be incorporated into the treatment process by early December, and will be operated by Council’s maintenance contractor, Ashburton Contracting Limited.

Share this article
Latest News
Algal bloom warning lifted for Lake Hood
Short water shutdown for parts of Rakaia east
Photo competition highlights our heritage hotspots
Changes for swim squad confirmed
Autumn What's On Guide, out now
Road Closures
DAVID STREET
from 23 Mar 7:00 to 10 Apr 18:00
SEAFIELD ROAD
from 2 Mar 7:00 to 10 May 19:00
FAIRFIELD ROAD
from 26 Jan 7:00 to 19 Apr 18:00
CATHERINE STREET
from 18 Mar 8:00 to 24 Apr 18:00
TANCRED STREET
from 23 Mar 7:00 to 27 Mar 18:00
View all Road Closures | Live map