New water main on Grove Street

Published: 29 August 2025

A new water main is being installed on Grove Street in September, between Carters Terrace and Wilkin Street, and drivers who regularly use that route can expect temporary road closures.

The work is being done in two phases, starting from the Wilkin Street end, and it will take about two months.

In the first phase, the intersection of Grove Street and Wilkin Street will be closed from 1 September to 26 September.

Access remains for residents and they have been advised of the work, which is being done by Rooney Earthmoving on behalf of Council.

An additional road closure on Grove Street at Carters Terrace will be advised in the second stage of the project.

The work involves digging a trench for the new water main and renewing household connections and fire hydrants.

New water mains are also being installed on Philip Street, in Ashburton, and temporary road closures remain.

Philip Street, from Walker to Grigg Street, will be closed until Friday 5 September as the project nears completion. Access remains for residents, and affected properties have been advised by letter.

One final road closure will be needed, for the intersection of Philip and Grigg Streets.

Share this article