Ashburton CBD Streetscape project resuming under Alert Level Three

With the country moving down to an Alert Level Three from Tuesday 28 April, the Council and contractors, Tru Line Civil will recommence work on the Ashburton CBD Streetscape Renewal project.
The reduced level allows for crews to get back to work upgrading the CBD. Several safety measures will be in place to ensure the wellbeing of staff and the community under the alert.
The initial work will include stormwater pipe installation on Cass Street; wastewater pipe installation on Tancred Street between Cass and East Streets; the construction of rain gardens on Cass Street; and connecting the new watermain pipeline that has been installed along Tancred and Cass Streets.
Tru Line Civil will be working hard to get the project back on track and minimise the impact it is having on CBD businesses, particularly as businesses look to reopen and recover when the Government eases lockdown restrictions.
Share this article
Latest News
Business awards celebrate local
$100,000 Lottery grant for bike skills park
Need tips from a pro for our heritage photo competition?
Watching brief on Tinwald bore
Cr Deb Gilkison: What surprised me most about joining Council
Road Closures
SEAFIELD ROAD
from 2 Mar 7:00 to 19 Apr 19:00
SMALLBONE DRIVE
from 15 Mar 6:00 to 15 Mar 15:00
MOORE STREET
from 3 Mar 6:00 to 6 Mar 18:00
RAILWAY TERRACE WEST
from 23 Feb 7:00 to 27 Feb 17:00
RACECOURSE ROAD (ONE-WAY)
from 25 Feb 19:00 to 26 Feb 6:00
View all Road Closures | Live map