Reconstruction starts on Isleworth Road near Hinds

Close to 800 metres of a rural road east of Hinds is the site of reconstruction work for the next four weeks, as the Council's contractor, HEB Construction cracks on with maintaining the district's roads.
A section of Isleworth Road, just east of the Chisnalls Road intersection is having pavement failures dug up and new aggregate and seal applied.
The work began on 22 March and is expected to take one month to complete, leaving the road in a better condition for drivers.
HEB Construction is responsible for all aspects of maintaining both sealed and unsealed roads across the district's 2,600km network including signage, road markings, drainage and bridges. The five year contract began in December 2020.
Motorists are reminded to drive with care and to obey the signposted road speeds while work is underway.
Share this article
Latest News
Consider the Flowers: Celebrating the life and work of Margaret Trolove
Lake Hood water update: Trial areas to be created
Keep your pets safe during fireworks celebrations
CE Hamish Riach: Reserve, hall boards in the spotlight
Cr Wilson to be Ashburton District's Deputy Mayor
Road Closures
BARNSWOOD ROAD
from 5 Nov 7:00 to 7 Nov 18:00
BURNETT STREET
from 10 Nov 6:00 to 12 Nov 18:00
CHALMERS AVENUE
from 30 Oct 7:00 to 4 Dec 18:00
CHALMERS AVENUE
from 20 Oct 7:00 to 21 Nov 18:00
SAUNDERS ROAD
from 25 Nov 6:00 to 12 Dec 18:00
View all Road Closures | Live map